IMAGE CREDIT : LINKEDIN |
Column retrofitting works to enhance the load-bearing capacity of an existing column by extending its foundation as part of retrofitting works.
Here are the 10 steps to execute the retrofitting works :
Step 1: Surface Preparation (Chipping)
- Chip the existing concrete surface of the foundation using a mechanical chipping tool or hammer.
- Ensure removal of all loose, weak, and deteriorated concrete.
- Expose the reinforcement bars, if needed.
Step 2: Surface Cleaning
- After chipping, clean the surface thoroughly:
- First using a wire brush to remove dust and particles.
- Then use a blower (compressed air) to eliminate all remaining debris and fine dust.
Step 3: Drilling for Dowels
- Drill holes at the required depth and spacing for dowel bars as per structural drawings.
- Maintain proper hole diameter to match the bar size and ensure firm anchorage.
Step 4: Dowel Bar Installation
- Clean the drilled holes using brush and blower.
- Inject Hilti chemical anchoring material (e.g., Hilti HIT-RE 500 or similar) into the holes.
- Insert the dowel bars immediately before the adhesive sets.
- Allow adequate curing time as recommended by the manufacturer.
Step 5: Reinforcement Fixing
- Install the additional reinforcement steel for the foundation extension and column base as per approved drawings.
- Tie the bars properly using binding wire to maintain correct positioning.
Step 6: Formwork Preparation
- Erect the formwork around the foundation extension as per the required shape and dimensions.
- Ensure formwork is rigid, properly aligned, and free from any leakage points.
Step 7: Final Surface Cleaning
- Just before applying bonding agent and pouring grout, clean the surface once again:
- Use a blower to remove all loose particles, dust, or foreign material from formwork and concrete surfaces.
Step 8: Application of Bonding Agent
- Apply Cempatch SBR 100 (or equivalent SBR-based bonding agent) on the cleaned surface.
- Ensure uniform application on all old concrete faces that will come in contact with new concrete/grout.
Step 9: Grouting / Concrete Pouring
- Prepare the grout mix using:
- Renderoc LA Xtra (non-shrink cementitious grout)
- Clean aggregates as specified
- Measured quantity of water to achieve the required flowability.
- Mix thoroughly using a mechanical mixer.
- Pour the grout carefully into the formwork, ensuring full compaction and no voids.
- Use rodding or light vibration if needed.
Step 10: Surface Curing
- Begin curing after initial setting of the grout/concrete.
- For curing we will use burlaps and put water on it 3 times in a day
Final Notes :
All materials and procedures must follow project specifications and manufacturer guidelines.
DISCLAIMER All The Information are posted in this website are best for my knowledge. These blog post are collected by various sources i.e. Official Documents/ Related Books/ Newspaper/ Related Website/ Government Notices/ Circulars and other reliable sources. Download any documents at your own interest, we do not refund or compensation any Amount against the Payment you have done. We do not Agree/ Responsible with its authenticity, all blog post in this website are only for information purpose. Any legal action against this Blog post are strictly at your own risk. Click Here to read our complete disclaimer. |