10 Steps for Column Retrofitting works by civilshape

IMAGE CREDIT : LINKEDIN

Column retrofitting works to enhance the load-bearing capacity of an existing column by extending its foundation as part of retrofitting works.

Here are the 10 steps to execute the retrofitting works :

Step 1: Surface Preparation (Chipping)

  • Chip the existing concrete surface of the foundation using a mechanical chipping tool or hammer.
  • Ensure removal of all loose, weak, and deteriorated concrete.
  • Expose the reinforcement bars, if needed.

Step 2: Surface Cleaning

  • After chipping, clean the surface thoroughly:
  • First using a wire brush to remove dust and particles.
  • Then use a blower (compressed air) to eliminate all remaining debris and fine dust.


Step 3: Drilling for Dowels

  • Drill holes at the required depth and spacing for dowel bars as per structural drawings.
  • Maintain proper hole diameter to match the bar size and ensure firm anchorage.


Step 4: Dowel Bar Installation

  • Clean the drilled holes using brush and blower.
  • Inject Hilti chemical anchoring material (e.g., Hilti HIT-RE 500 or similar) into the holes.
  • Insert the dowel bars immediately before the adhesive sets.
  • Allow adequate curing time as recommended by the manufacturer.


Step 5: Reinforcement Fixing

  • Install the additional reinforcement steel for the foundation extension and column base as per approved drawings.
  • Tie the bars properly using binding wire to maintain correct positioning.


Step 6: Formwork Preparation

  • Erect the formwork around the foundation extension as per the required shape and dimensions.
  • Ensure formwork is rigid, properly aligned, and free from any leakage points.


Step 7: Final Surface Cleaning

  • Just before applying bonding agent and pouring grout, clean the surface once again:
  • Use a blower to remove all loose particles, dust, or foreign material from formwork and concrete surfaces.


Step 8: Application of Bonding Agent

  • Apply Cempatch SBR 100 (or equivalent SBR-based bonding agent) on the cleaned surface.
  • Ensure uniform application on all old concrete faces that will come in contact with new concrete/grout.


Step 9: Grouting / Concrete Pouring

  • Prepare the grout mix using:
  • Renderoc LA Xtra (non-shrink cementitious grout)
  • Clean aggregates as specified
  • Measured quantity of water to achieve the required flowability.
  • Mix thoroughly using a mechanical mixer.
  • Pour the grout carefully into the formwork, ensuring full compaction and no voids.
  • Use rodding or light vibration if needed.


Step 10: Surface Curing

  • Begin curing after initial setting of the grout/concrete.
  • For curing we will use burlaps and put water on it 3 times in a day


Final Notes :

All materials and procedures must follow project specifications and manufacturer guidelines.


Disclaimer : All The Information are given in this post/ article are best for knowledge. these post/ articles are collected by various sources i.e. official documents/ related books/ newspaper/ internet/ govt notices/ circulars and other reliable sources. Download this documents at your own interest, we do not refund or provide compensation against the payment. We do not agree/ responsible with its authenticity, we have just post here for kind information. Any legal action against this post/ article are strictly at your own risk. Click Here to read our disclaimer.